Version Number | Developer | Date | Time | Notes |
2000..161 | KJT | 06/29/2007 | 10:38:06 | Added KeyLok support. |
2000..160 | MRM | 05/25/2007 | 14:52:58 | Fixed Select from Othe Library to bring in blank Mtl Code items to existing estimate |
2000..159 | MRM | 05/04/2007 | 16:23:21 | Fixed Zoom on UR field in Modify Estimate to not use FT field |
2000..158 | MRM | 04/24/2007 | 16:48:50 | Added a program to force the creation of the IKEFP Logical Name so VTO will find color file. Fixed Est Other Cost Screen Scroll Problem |
2000..157 | MRM | 04/23/2007 | 14:47:10 | Added 'S'pray Top Flange to Fill Flute Options of 'Y'es and 'N'o. Added Detail Sort Buttons for Size and Rec# |
2000..156 | MRM | 04/23/2007 | 11:03:59 | Corrected Problem in updating VTO colors during recalc. |
2000..155 | MRM | 04/18/2007 | 12:14:30 | Added Material Code delimiter to Recap Other Costs |
2000..154 | MRM | 04/02/2007 | 15:38:36 | Added Zoom function to ULDesign Code Screen when in Create Mode. Added Export/Import of Material Yields |
2000..153 | MRM | 03/30/2007 | 15:49:06 | Added Export of ULDesign Name and Bags/Gallons Switch if doing all UL Design codes for a Mtl Code |
2000..152 | MRM | 03/29/2007 | 16:33:21 | Increased the size of the ULDesign Tab Screen |
2000..151 | MRM | 03/23/2007 | 12:58:58 | Added Ability to import Many ULDesigns for a MTL Code |
2000..150 | MRM | 03/19/2007 | 15:52:48 | Added Qty Indicator 'TA' Total Area = (JA+CA+BA+DE) Added Qty Indicator 'SA' Total Seal Area = (JA+CA+BA+DE) if Floor 'Include in Seal Area' Check Box is checked in Floor Takeoff Screen. |
2000..148 | MRM | 03/01/2006 | 17:44:19 | Changed Call VTO to be like other IKE modules |
2000..147 | MRM | 02/06/2006 | 13:47:54 | Added ' 1' - 'One' to QIN Table, it allows for the use of fixed cost or MD Recap Other Items |
2000..146 | MRM | 01/24/2006 | 11:43:36 | Added CD - Crew Days back into QIN Table, it got deleted in release 144. |
2000..145 | MRM | 11/16/2005 | 15:34:13 | Changed Estimate Selection program to correct program in the Thickness Report Prompt Program. |
2000..144 | MRM | 11/15/2005 | 15:19:19 | Added new Quantity Indicators and added Boxed Steel capabilities. |
2000..143 | MRM | 11/04/2005 | 12:20:47 | Corrected VTO menu card logical name. |
2000..142 | MRM | 11/03/2005 | 11:12:05 | Added ability to auto change VTO menu card to Fireproofing.menu via a logical name. |
2000..141 | MRM | 07/08/2005 | 13:37:48 | Added a Delete Detail Record by Record Number Utility. |
2000..140 | MRM | 04/08/2005 | 13:06:40 | Added Cost per Bag-Gal statistics to bid recap report. Corrected Margin% calc on bid recap. |
2000..139 | MRM | 01/13/2005 | 15:06:43 | Changed so zero WD does not look up Thickness. Changed Modifier Screens to Show WD and Size Thickness Lookups. Added Copy UL Design Program |
2000..138 | MRM | 11/12/2004 | 16:08:02 | Added a Batch Create Column WD Thickness Program for Intumescent Products. Changed some Reports for Bags/Gals BF/MILS |
2000..137 | MRM | 10/19/2004 | 15:35:37 | Changed Bid Recap Report so it has a lanscape printing option. Not printing right columns in portrait on all types of printers. |
2000..136 | MRM | 09/13/2004 | 14:51:15 | Changed Bid Recap Report and made it wider to print larger numbers |
2000..135 | MRM | 03/19/2004 | 16:28:17 | Changed Prod Screen so you can input in zero amonts for Machines, Nozzels, Setups. |
2000..133 | MRM | 10/28/2003 | 17:32:39 | Corrected Steel Shape program to allow for input of new Shapes. |
2000..132 | MRM | 10/28/2003 | 16:06:49 | Added WD Ratio Export and Import Programs |
2000..131 | MRM | 10/27/2003 | 14:15:17 | Added MILS and Gallons verbage to Report Headers |
2000..130 | MRM | 10/24/2003 | 16:40:04 | Added MILS verbage to Online Calculation Screens. Corrected MILS per LF by multiplying by 1000 |
2000..129 | MRM | 10/23/2003 | 18:21:58 | Changed the calculate BF to Actual Thickness Decimal from Thickness Table instead of Lookup Decimal to get more pricision for MILS |
2000..128 | MRM | 10/22/2003 | 16:36:19 | Increased Field Size of, Yields to allow for 4 Digits, Thickness to allow for 3 Digits. |
2000..127 | MRM | 10/22/2003 | 14:33:00 | Fixed (Added Thick Add # ) so it would work correctly when using a Detail Line Thickness Override. |
2000..126 | MRM | 10/02/2003 | 16:31:18 | Added Thick Add # to Steel Size Table. Fixed Floor Prod Field to update correctly. Fixed Deck Overide Thk lookup. |
2000..125 | KJT | 04/07/2003 | 16:11:03 | Added Color Defaults by Thickness. Added Color to thickness report and Override screen. VTO version 2003.2.0 or higher is needed to use this feature. |
2000..124 | MRM | 03/28/2003 | 11:25:05 | Added Bags/CD to Summary Reports |
2000..123 | MRM | 03/28/2003 | 10:45:24 | Added Bags/ND to Summary Reports - Changed Detail Take-off to only Auto Skip Mtl Code in Create Mode |
2000..122 | MRM | 03/05/2003 | 15:33:03 | Changed Other Cost Library to create records correctly.
|
2000..120 | MRM | 02/24/2003 | 17:59:56 | Added Delete Access Key Program to Help Menu |
2000..119 | MRM | 02/04/2003 | 17:39:37 | Added Bags/MD to Summary Reports - Corrected Floor Prod problem in Floor Setup - Corrected Zoom problem to FR code in UL design. |
2000..118 | MRM | 01/03/2003 | 12:15:41 | Changed the Change Material Code Utility in Take-off Screen to have an All floor option.
Added Other Cost Markup to Bid Price in Recap. |
2000..117 | MRM | 11/15/2002 | 11:09:09 | Added Select Crew Code and Rate to Est Master. Fixed Other Color. Fixed Col Flute Ex Flag Reset Prob. Added UR Range to Est. Fixed delete floor to delete Floor Other Record. |
2000..116 | MRM | 11/06/2002 | 11:08:27 | Added New Global VTO fields for Floor Take-off. |
2000..115 | MRM | 11/04/2002 | 11:05:58 | Added a Batch Estimate Utility to change Take-off Quantities by creating a mutilplier from two different scales. |